Project Plan Documents
Milestones
Task |
People Assigned |
Target Completion Date |
---|---|---|
Surveillance scan capability at Marshall |
Group |
(completed) |
Full PPI and RHI scan and GUI control capability |
Dixon/VanAndel/Loew |
(complete) |
Install and configure git repository at CSU and EOL |
VanAndel/George |
2009-03-06 (complete) |
Rewire S-Pol receiver and STALO boxes |
Emmett |
2009-02-27 (complete) |
Convert HAWK time series process (RVP8TsTcpServer) to use common time series format (4.4) |
Dixon |
2009-03-13 (complete) |
Convert CHILL time series process (AcquisitionServer) to use common time series format (4.4) |
George |
2010-06-01 |
Build buffer board for S-Pol timing signals (breakout box) (waiting on design info from Eric) |
Emmett |
2009-06-20 (complete) |
build cables to attach Power PMAC to S-Pol pedestal servo amps, S/D board |
Loew/Phinney |
2010-03-30 (complete) |
Replace servo amps in S-Pol |
Phinney |
2009 -12-01 (complete) |
Need new fault board for S-Pol Servo Amps |
Strong |
(complete) |
Antenna Pattern test @ Marshall : setup antenna on CP-2's concrete pad. |
Strong/Phinney/Emett/Bobka |
(complete) |
Cleanup wiring in S-Pol transmitter container |
Emmett/Holden |
2009-04-03 (complete) |
Install new power meters at S-Pol (4.5) |
Holden |
2009-04-03 (complete) |
Convert moments calculation server to use common time series format (4.6) |
George/VanAndel |
2009-04-10(complete) |
Convert HAWK moments calculation software (iq2dsr) to use the common time series format (4.6) |
Dixon |
complete |
Write SDB to Dsr real-time translator (to view CHILL moment data with CIDD) |
Dixon |
complete |
Install NEXRAD/FAA transmitter at S-Pol (2) |
Bobka/Emmett |
2009-04-17(complete) |
Rewrite CHILL system control software (DTctl) (4.2) [completion depends on Power PMAC] |
Brunkow/George |
2009-11-30 |
Initial Power PMAC development, configuration and testing for S-Pol |
VanAndel/Loew w help from Brunkhow |
2009-12-04 (complete) |
Integrate instrumentation server (calsrv) at S-Pol (4.5)with support for 2 dual-channel power meters |
VanAndel |
2009-01-29 |
Build and test new digital waveform generator board (4.1) - not needed by S-Pol |
George |
2010-02-27 |
Integrate CHILL transmit control server (txctl) and digital waveform generator at S-Pol (4.1) |
VanAndel/Emmett/Farias |
2009-12-15(complete) |
S/D converter for S-Pol & Eldora Test Pedestal |
Loew/Farias/Gales |
2009-12-01 (complete) |
Complete S-Pol setup at Marshall |
Bobka/Gales/Emmett/Holden/Phinney/Rivas/Strong |
2009-12-01(Complete) |
Integrate Power PMAC at S-Pol (4.3) |
Loew/Brunkow/Gales/VanAndel |
2009-12-20(complete) |
Integrate CHILL system control software (syscon, aka DTctl) at S-Pol (4.2) |
VanAndel/Dixon/Loew |
2009-12-15(complete) |
Acquisition Server Software (control RVP8 and Moment generation) |
Dixon/VanAndel |
2009-12-30 (complete) |
Initial Antenna/System control GUI |
VanAndel |
2010-04-15 (complete) |
Install HAWK processing system |
Dixon |
2010-04-15 (complete) |
Install CIDD |
Dixon |
2010-04-15 (complete) |
Install CSU Engineering Display |
Dixon/VanAndel |
2010-04-15 |
Update Engineering Display with hot keys and other needed capabilities (from old E. display) |
Dixon/VanAndel |
2010-05-15 (complete) |
ATE installed with software control of calibration equipment |
Dixon/Morley/Emmett |
2010-11-30 |
S-Pol unattended operation |
group |
2010-09-15 (complete) |
PID/precip-rates/refractivity algorithms operational |
Dixon/VanAndel/others |
2010-12-10 |
Define CF-compliant netCDF common data format for integrated radar data (moments). |
Dixon/Van Andel/CHILL staff |
2009-12-15 (complete) |
Real time vector winds from CHILL and S-Pol data |
CSU Staff |
2012-07-015 (After DYNAMO) |
Gridding multi-radar data (S-Pol, CHILL, NEXRAD, Pawnee) |
Dixon/VanAndel/CHILL staff |
2012-07-015 (After DYNAMO) |
Sun Scan, vertical pointing (calibration) capability |
Dixon |
2010-11-31 |
Automated cross-polar power technique for Zdr calibration |
Dixon/Morley |
2011-01-31 |
Other/Future Work
- Generate detailed CHILL documentation: Joe, Jim, Dave
- Antenna/System Control
- Create Requirements document for S-Pol, based on current capabilities of the "Lutz" Antenna/system control software
- GUI : Joe
- Design
- Implement
- Integration test
- web based system control: ???
- Time Series
- build time series utilities (possibly based on John Hubbert's Fortran program)
- FORAY2 to read/write radar data formats : Dennis
- design
- document
- implement
- Archiving
- modify archiver to write CF-compliant netCDF(4)
- port S-Pol tape archiving scripts/programs to backup disk files to tape
- GUI for operator to control archiving
- Calibration
- finish documentation for Frank's Labview code
- automated calibration procedure for S-Pol
- implementation, including utilities to compute calibration values from ATE measurements
- documentation
- implement automated calibration on CHILL
- Remote control and monitoring
- environmental - temperature, air flow, voltages
- remote console, power control for key computers
- remote monitoring of computers, product generation (NAGIOS?)
- remote monitoring of new transmitter.
- Technology to investigate:
- Measurement computing PCI-DIO48H-RT with Comedi driver
- Sixnet ET-GT-485-1 Ethernet to RS485
- Advantech ADAM series
- Websensor EM01B (Nagios compatible)
- ENVIROMUX Server Environment Monitoring System (Nagios compatible) http://www.networktechinc.com/
- Scientists Display
- write requirements
- select JADE or IDV or another solution
- implement missing features
- integrate into IWRF
- Advanced radar algorithms
- refractivity - rewrite, using FORAY2
- automate quality control
- Computer system management
- cfgengine or equivalent to update passwords, hosts files
- backup, recover system
- recovery plan, including spares for field deployment
2 Comments
John Hubbert
25 June 2009 IWRF meeting notes:
1) S-Pol timing card
The timing card is mostly done. The buffer card for all of the timing signals produced by the
timing card is underdevelopment. The buffer board should be completed by the end of July.
2) Power P-MAC
The DETA TAU class on the P-PMAC is on 20 July in L.A. Brunkow will likely
attend and the engineer from EOL is TBD -- likely Loew?
3) Antenna contol GUI
Van Andel is working on a prototype radar control GUI. At the next meeting, 27 July, 10AM @ CHILL,
Van Andel will make a presentation. WT (instead of QT) is being used for this initial GUI design.
GUI will accommodate remote S-Pol control.
4) S-Pol antenna surface roughness measurements were made by GEODETIC. These measurements will
be used to determine the feasibility of adjusting the S-Pol dish and to evaluate the crosspolar
coupling limitation imposed by the dish.
21 May 2009 IWRF meeting notes:
1) Time card
S-Pol time card is about 90% done. Buffer board needs to designed and
constructed. Mid-july is the projected completion date (Eric).
This is the old CHILL timing board.
2) Power PMAC
The power PMAC antenna controler box is in but needs documentation.
There is a 3 day class to be offered by delta tau this summer sometime.
Joe and Dave intend to take this class.
3) Radar system control
CHILL's current control system is termed "DT" for Delta Tau.
S-Pol could use this control package for S-Pol. It is designed to
operate using the current CHILL time series format. However, CHILL staff will be creating a new control software
package perhaps by the end of August. Also, S-Pol has
adapted the new IWRF time series format so there is some question
as to the best way to proceed forward with the S-Pol system
control software. S-Pol will plan to wait for new CHILL system controller, but may implement simple, distributed control of radar in the interim to further radar testing.
4) Antenna control GUI
Van Andel will design a GUI based on the old S-Pol
GUI and CHILL staff experience. Recently ARC adapted
gthe old S-Pol GUI and this ARC GUI could be reviewed
also. Van Andel will consult with the appropriate EOL and
CHILL staff, create an initial design and then organize a demo
for the first part of July or another time mutually agreeable time
date to coincide with IWRF staff face-to-face meeting.
5) FORAY II
Flanigan should complete FORAY II by the end of August. This
library of data format translation routines will help both staffs
with data management.
6) RVP8
The time series output from RVP8 needs to changed to match the new accepted
IWRF time series format. Dixon says this is a relatively simple task.
7) S-Pol antenna
The S-Pol reflector will be evaluated 27-29 May. At that time the options for
S-Pol antenna improvement can be revisited.
8) HAWK at CHILL
HAWK/TITAN/CIDD are now operational at CHILL. Dixon will continue
to assist CHILL staff with HAWK system, data format issues related to this.
Determining the best way for CHILL staff to adapt to IWRF time series
format is an important part of this.
John Hubbert
S-Pol System block diagram