9/11
Base trailer is partially set up - leveled and generator hooked up, porch etc. all thanks to John and Laura.
Fuel tanks for ISFS and ISS in place.
Anchors set for NEAR, 449, and base towers
Concrete blocks staged for helicopter lift
Tomorrow we are set to install anchors at FAR, meet with Brad Andes and confirm anchor pull specs with Ken Shively.
We may even get to play with heavy steel......

9/12

Some good news and some bad.....

We got anchor verification for NEAR, BASE , and 449 today from Ken Shively, but FAR has one anchor we have yet to get to "hold".   Will attack that anchor later in the week as we have other issues to attend to.
Met with Brad Andes today and went over the "no go zone" at rim and unfortunately, the NE anchor was in that zone.  I will move the site accordingly and will keep you informed as to our progress.
Over all I feel we are on track and moving ahead.
The next few days will be spent on getting the platforms ready for the rim site and surveying how the tower will fit into the new approved "go zone".