Ok, we got the anchors installed at FAR thanks to Chris, John, and Tim.
(hard working boys all)
Laura and I got the RIM site mapped out (looks better than I had expected), and the base plate installed.
steel Steel platforms are 99.9 % put together, just missing 3 bolts which we got in the nick of time in flagstaff - Fastenall stayed open for us till we were able to get there, otherwise we would have had to wait till monday morning. 
Good news about the permit being in Steve Atkins hands - we may be able to go vertical sunday or even sat afternoon!
Dave W. will arrive sunday evening and stage on monday.
Got an email from Greg @ air west requesting I call him asap......
Hoping there is no bad news....will call him first thing tomorrow morning.