Windy day so we didn't increase the tower height of NEAR, but we were able to plumb the 70 ft already in place.
Anchors were installed at FLOOR, and Ken was notified. He will inspect all remaining anchors on friday.
John and I went to Flagstaff urgent care.   John has a fractured ring finger on his right hand, I have a strained ligament in my right foot. Nether aliment will hinder our work.

September 19

got to 140 ft today at NEAR

September 20

Anchors passed at FAR, RIM and FLR.  RIM failed with base plate for tower but timbers were added to pass inspection.

Soil sensors installed at FLR while anchors were being checked.

September 21

The tower at near is now finished, including AWM's , bird flappers, and beacon.  We plumbed and tensioned it also.
Got a start on rim, but high winds prevented us from going vertical.  Rim is staged and ready to build weather permitting.
Will attempt to put up some 40 ft towers tomorrow if we can't work om rim.
September 22

EXTREMELY windy today.  FLR tower was erected.