Another banner day!
Kudos to my fabulous team, Chris, Gordon, and Gary Granger.
NEAR is instrumented except for a Krypton.
We also put up BASE and instrumented the 449 tower (wind head).

September 29

far was instrumented (needs press hose and grounding of dsm and soils turned on)

base was mostly instrumented (needs 10 m sonic and networking)
networking was worked on at near and rim
solar and rad was worked on at near

September 30

far is finished (installed dsm gnds, turned on soils mote and installed press port hose)near is finished (beacon pwr cable, kH2O installed, mote and battery and cables for the SPN 1 sensor,  dressed tower cables, etc.
rim is finished
lidar power and Ethernet is installed

Our in ops in the crater was very productive.  These are the updates for the crater...

...Updates:
Met tower instrumented BUT had some complications:
        -no power cable to solar panels
        -no ethernet cables to UofU LIDAR
        -solar stand (dark horse) is not in place
Pressure stands:
        -all SSW, S, NNE and FLR pressures have been placed and check by Sabastion
        -no sonic towers have been erected but the pressure transducers have been turned on for communication purposes
        -Solar panels have not been brought to areas of these sonic sites
Poopy
        -Crapper has been installed on the Westside of mine fence
        -Poopy buckets need filled for usage.
        -Tied down for high winds