Another banner day!
Kudos to my fabulous team, Chris, Gordon, and Gary Granger.
NEAR is instrumented except for a Krypton.
We also put up BASE and instrumented the 449 tower (wind head).
September 29
far FAR was instrumented (needs press pressure hose and grounding of dsm and soils turned on).
base BASE was mostly instrumented (needs 10 m sonic and networking).
networking Networking was worked on at near and rim.
solar Solar and rad was were worked on at near.
September 30
far FAR is finished (installed dsm gnds, turned on soils mote and installed press pressure port hose)
NEAR near is finished (beacon pwr cable, kH2O installed, mote and battery and cables for the SPN 1 sensor, dressed tower cables, etc.
rim RIM is finished
lidar power Power and Ethernet is installed for ASU lidar.
Our in installation ops in the crater was were very productive. These are the updates for the crater...
...Updates:
Met tower instrumented BUT had some complications:
-no power cable to solar panels
-no ethernet cables to UofU LIDAR
-solar stand (dark horse) is not in place
Pressure stands:
-all SSW, S, NNE and FLR pressures have been placed and check checked by SabastionSebastian.
-no sonic towers have been erected but the pressure transducers have been turned on for communication purposeschecks.
-Solar panels have not been brought to areas of these the sonic sites
Poopy PortaPotty
-Crapper PortaPotty has been installed on the Westside of mine fence
-Poopy buckets Composting need filled for usage.
-Tied down for high winds