...Updates:
Met tower instrumented BUT had some complications:
        -no power cable to solar panels
        -no ethernet cables to UofU LIDAR
        -solar stand (dark horse) is not in place
Pressure stands:
        -all SSW, S, NNE and FLR pressures have been placed and checked by Sebastian.
        -no sonic towers have been erected but the pressure transducers have been turned on for communication checks.
        -Solar panels have not been brought to the sonic sites
PortaPotty
        -PortaPotty has been installed on the Westside of mine fence
        -Composting need filled for usage.
        -Tied down for high winds

October 1

FLR is complete.  All instruments are communicating BUT sonics at SSW2 and SSW4.  Towers are installed at those two sites for pressure but no sonics.  Hardware and ECHO boxes are at tower sites for sonic install.  Installed one 64W panel at each tower hoping to get enough charge.  SSW2 seems to have good sun but not SSW4...extremely steep.  Panel is resting on sonic box that is held up by piled rocks.  DO NOT CLIMB THESE TOWERS!  PortaPotty is ready for use.  Need toilet paper.