Planning:

- Permitting was difficult. Must be a budget line item.

- Site visit was important for comms testing.

- Need a good relationship with UCAR contracts early in project.

Pre-project testing:

- 2+ weeks of staging area testing was critical for start of ops.

- Need to pay more attention to mote comms during testing.

Training and Safety:

- must do tower training, tower rescue training. Bob Wiley has organized tower training in Dec.

- need training on motes, DSMs, base systems, XML

- AED, first aid

- Helo ops were difficult

- Must notify Bob Wiley on any injury.

Packing:

- In general a very good job was done in organizing equipment for each station, with color ribbons, rubbermaid tubs

Packing:

- Still need to take soil cores: bring oven/scales/soil install kit (buy a second oven and scales for trailer?)

- Replace gas can (cheapo Walmart can's spout broke)

Setup

- Setup was slowed each time anchors needed testing.  Would have been nice to install anchors a week or two before-hand.

- Need to get prior permission from dir office when using non-ISFS staff.  Use temp workers?

- should have a pow-wow of on-site staff each morning

- need additional harness, ascender

- need new winch/capstan, new rope

- need portable generator

- can we improve procedures for plumbing tower, guy wire building and tensioning?  Use come-alongs?

Sensors:

- need to check/replace radiometer desiccant prior to project

- downlooking PYG at far had short in wire from thermopile

- Schwartzeneggers need refurbishing

- two serializers became noisy.  Need to replace or get rid of.

...

- SPN1 isn't perfect.  Sent note to manufacturer.  They think it would be useful to run as a serial sensor and have the option for "TEST" mode.

- Still need to take soil cores: bring oven/scales/soil install kit (buy a second oven and scales for trailer?)

- Qsoil response not normal in this soil.  Need manual calibration.  What should the strategy be here?  I actually liked having a test plot near the base.  In any case, soil quite dry during most IOPs.

...

- shorter studs on CSAT electronics boxes; suggest using lock nuts (like TRAM) instead of nylocks. Dedicate some mounting plates for sonics that are small enough to ship in the box. Could one plate work for Rohn and pump-up towers?

Power:

- ISS was happy with the solar trailer

- Still don't understand mote diodes.  Having a diode between charger board and battery caused failures.  Had no failures with diode removed.  Considering charge controller redesign.

Mote:

- Disabling radio reset was necessary. Xbees had new firmware since PCAPS.

- Xbee radios worked loose, need to be better secured. Oxidation was present.

- Spare mote 15 wouldn't come up plugged in to console cable.  (Something I've done wrong?)  Labeled Labelled.

- Power motes feed power into DSM interface panel.  Something should be changed.

...