Station Status: All up.
Main Tower
Gordon just got the TRH sensor at 42 m on the main tower up and running by restarting it.
Station 1
Soil core at S1 completed. Baking now.
...
Cleaned the EC150 3D sonic cable end with contact cleaner and cleaned the cable receptacle. It restarted with success and is collecting data.
Reshot boom angles of sonics at 10 m and 3 m. The 2D sonic at 10 m had an azimuth of 319 deg. The 3D sonic azimuth was 227 deg.
...
Sensor Status:
T/RH: 42m TRH now not reporting. Power cycle does not bring it backcame back after being power cycled. Others okay (note that S1,2,9,10 are wired not to report Ifan).
P: ok
2D Gill: ok
csat u,v: ok
csat ldiag: ok
csat w, tc: ok
3D RMY: ok
EC150: ok
motes: ok
Wetness: ok
radiation: ok
Tsoil: ok
Gsoil: ok
Qsoil: ok
Cvsoil: Ready to manually read sensor
Rainr: ok, reported about 1/4" today.
Vbatt: Vbatt.tower at 12.6V on 10/9