ISS is running with setup largely complete - the last major item was installation of acoustic shielding surrounds for the wind profiler RASS, which was were installed today. RASS was turned on this afternoon, as usual running for 5 minutes every half hour.  It is currently measuring virtual temperature up to about 600 - 700m altitude, with the amp running at moderate power - about 7 VAC (amp output), which produces around 115 dB at the speakers (50 dB at 30m horizontally out from the shielded speakers).  Winds are being measured up to the 2 - 3km level.

...