Installed sensors and powered up v05 without incident. Although it's relay (rnw06) is not up yet, it was able to establish a network connection with another router and transmit.
Left to do at site:
- hose clamp grounding wire to tower
Installed sensors and powered up v05 without incident. Although it's relay (rnw06) is not up yet, it was able to establish a network connection with another router and transmit.
Left to do at site: