9/19/16
Summary: Rain started as soon as we got to the trailer 8:30
Off and on all day; nevertheless did a boat tour to 15, 9, 1
All stations look good this morning, until the rain started
Actions past 24 hours:
- Yesterday (9/18) was a "dead day" (day off)
- Shift change: Andy arrived Thurs, Gary left Sat, today is Steve O's first day, Steve S. leaves tomorrow
To dos:
- Reshoot boom angles (just because...)
Sensor Status:
- Lost everything from s9 for 10min overnight in the UDP data; I'll check if the raw_data are okay
T/RH: ok
P: ok; Pirga still lower by about 1mb
2D Gill: ok
csat u,v: ok
csat ldiag: ok
csat w, tc: ok
EC150: ok
motes: ok
Wetness: ok
radiation: ok
Tsoil: ok
Gsoil: ok
Qsoil: ok
Cvsoil: still need to have John/Steve S come up with a fix (in Boulder)
Rainr: isn't being covared, doesn't show tips in cockpit, even though it is raining. Hmmm.
Vbatt: ok