Another sunny day although very chilly in the morning with lots of frost and fog to the south of the valley from the Deer Creek Reservoir.

At the profiler site, the new external power amplifier box was cabled up, cables from the profiler to the trailer were laid out, power was hooked to the trailer, the RASS dishes were assembled and equipment in the trailer was organized.

At the Railway service pad site, there was more unpacking and sorting of equipment in the lidar/storage trailer, the lidar platform was assembled and equipment was transported between sites.


Working on the Modular Profiler power amplifier and the lidar plaform.