Spent the day on the supersites, both to prepare for snow/cold tomorrow and to secure the sites against cows:

DCS:

  • Drilled and set corner posts and T posts at TT site and 2 scintillometer sites.
  • Set TT boom clamps (except one) and added top Rohn section.  A bit involved since a) we were missing a bunch of nuts&bolts b) I had mistakenly had the TRH and Rad booms interfering with each other c) I also had forgotten that the bottom TT section needs a slotted clamp.  Found that Sebastian's booms will work fine.

PRS:

  • Drilled and set corner posts
  • The same setting of TT clamps.  This tower is complete now.
  • Found the remains of the pre-installed heat flux plate

Base:

  • Porta potty is installed
  • ISS lidar is installed

If anyone finds a Best Western room keycard at the sites, it (was) mine!