All work at DCS:
- Almost completed fence work
- Sebastian worked on setting up the radiometer intercomparison
- Rohn tower and Ott installation completed (sensors and cabling)
- Worked a bit on the Darkhorse (DCSG)
- Prepped radiometers in base
Still to do at DCS:
- Install soils
- Install PSPs
- Install NR01 & wetness
- Cable up DCSG sensors and motes (yes, 2)
- Almost everything sensor/cabling/power related on the TT itself
Also scheduled to work through the PRS radiometer stuff with Sebastian tomorrow.