4" of snow did come overnight, but not really an issue for site access.
Tomorrow Steve leaves and the rest of the crew takes a hard-earned down day!
UP: Set up
PC: Set up
This completes the basic set-up of satellite sites, though there still is a punch list of items (such as added snow depth and CS125 sensors). The only remaining sensors to deploy are on the TT at PRS.
Gary did a (manual) round of update to most, if not all, satellite sites. Supersites have not been updated since they do not yet have power set up.