Yesterday had the shift change from set-up to (almost) operations.  Dan, Kurt, Isabel, and Ned are now gone, with Gary leaving tomorrow.  Kate and I now have the comm. 

Winds have been stronger than desired, so no IOPs, which is good since several things are not yet operational. Chief among these is the CTEMP fiber-optic temperature sensor, which has had several issues and at the moment is only half laid out.  There also is an issue with the scanning laser system.  All of these are being resolved.

Thanks to the set-up crew, we have the primary 4 towers and the 6 pressure towers all up and running, though with several things to go: