Sunday Sept 17 Bruce arrived at the REAL about 0900 PDT.
This morning's 500 mb chart:
The winds are calm and there are high cirrus with scattered alto-cumulus clouds.
Clouds looking East 0900 PDT
Clouds looking West 0900 PDT
The raid disk was hot swapped out and is rebuilding - 1515 PDT.
Photos from the hot swap from left to right - 1 the server with the bad drive removed, 2 the new drive (in plastic case) and the old drive in the carrier, 3 the old drive removed from the carrier, 4 the new drive, the server with the new drive installed. fields
The server manufacturer (Colfax international) was very helpful in restoring the server to full health. There is a very long string of emails between Colfax support, Shane and Bruce that identified the bad disk and allowed us to make a field repair.
Nice wind field estimates today - below is an example.
Above: REAL PPI and wind field estimate 1528 PDT
Below: REAL rooftop cam at 2:30 PM
REAL rooftop cam at 7:14 PM
This evening's 500 mb chart: