CCSM/ESMF joint meeting
Tuesday, March 7th, 3:00-4:00pm
Damon room
Erik Kluzek, Mariana Vertenstein, Cecelia Deluca
ESMF Build status
- New release resolves issues from Brian Eaton
- Cray-X1 is working,
- NEC - working on compilation issues, probably few months out
- Linux - we wanted Lahey (so provided Bangkok) (Pathscale – later)
ESMF Core Team - Chung – Porting and optimization
- Two new hires
- Don – visiting scientist
ESMF design overview
Shows basic high-level picture and way time-sequencing works - ESMF-Stage1DesignOverview
Review results of CCSM/ESMF Stage-1 meetings
Show the high level picture of the complete sequential system - Feb 24, 2006 (Basic high level picture)
Some run-loop alturnatives and issues for fully concurrent system - Mar 3, 2006 (Some run-loop alturnatives and complexities for concurrent model)