- inventory: job boxes, manfrottos, otts, shts, ???
- TT license plates
- OTTs to base from lidar trailer
Timing:
Steve runs to Logan to pick up repaired sonics?. The repairs have been delayed.- All drives to/from site (especially TTs) should occur in the morning, when the ground is harder. Perhaps this means caching stuff on site and removing the caches in the mornings?
- Steve already there; Clayton arrives 2/23 (last day of ops)
- strip all towers of instruments, pack in base
- start with satellites, since Sebastian won't be available Thurs AM
- remove heating stuff from CSATs
- good luck removing soils!
- figure out how to pack NR01s with ventillation systems
- provide some assistance to remove PI sensors
- sort out NCAR vs. UU radiometers/ventillators (relatively easy: CVF3s to UU, CVF4s to us; Bindered sensors to us, rest to UU)
- return HRXLs to UU – just cut cables?
- return CS125s (DC is ISS's, I think)
- return to remove satellite infrastructure, pack in 16' Penske
- Rohn towers/bases/guys to 16' Penske
- solar/job box to 26' Penske
- manfrotto/booms to 26'
- cables sorted to base
- DSMs to 16'
- strip all towers of instruments, pack in base
- RSF tech available?; Tony, Chris arrive 3/2ish
- coil up supersite power cables, pack in Penske for Boulder
- help remove cc solar panels (hope we can drive in, or rent tracked vehicle from equipment place, or leave in place till later)
- remove fencing to 16'
- pull TTs out to BW road
- someone pulls Ubiquiti from school roof
- need to pull out everything from DCS by 1 Mar
...