  • inventory: job boxes (3 in storage), manfrottos, otts (5 in lidar trailer, 1 in base), shts (only 13 in base), ???
  • TT license plates (now in base) (dcs now done)
  • OTTs to base from lidar trailer
  • break cables out of ice (3 spots for DCS)

Timing:

  • Steve runs to Logan to pick up repaired sonics?. The repairs have been delayed.
  • All drives to/from site (especially TTs) should occur in the morning, when the ground is harder.  Perhaps this means caching stuff on site and removing the caches in the mornings?
  • Steve already there; Clayton arrives 2/23 (last day of ops)
    • strip all towers of instruments, pack in base
      • start with satellites, since Sebastian won't be available Thurs AM 
      • remove heating stuff from CSATs
      • good luck removing soils!
      • figure out how to pack NR01s with ventillation systems
    • provide some assistance to remove PI sensors
      • sort out NCAR vs. UU radiometers/ventillators (relatively easy: CVF3s to UU, CVF4s to us; Bindered sensors to us, rest to UU)
      • return HRXLs to UU – just cut cables?
      • return CS125s (DC is ISS's, I think)
    • return to remove satellite infrastructure, pack in 16' Penske
      • Rohn towers/bases/guys to 16' Penske
      • solar/job box to 26' Penske
      • manfrotto/booms to 26'
      • cables sorted to base
      • DSMs to 16'
  • RSF tech available?; Tony, Chris arrive 3/2ish
    • coil up supersite power cables, pack in Penske for Boulder
    • help remove cc solar panels (hope we can drive in, or rent tracked vehicle from equipment place, or leave in place till later)
    • remove fencing to 16'
    • pull TTs out to BW road
  • someone pulls Ubiquiti from school roof
  • need to pull out everything from DCS by 1 Mar

...