  • inventory: job boxes (3 in storage), manfrottos, otts (5 in lidar trailer, 1 in base), shts (only 13 in base), ???
  • TT license plates (now in base) (dcs now done)
  • OTTs to base from lidar trailer
  • break cables out of ice (3 spots for DCS)
  • pack up battery charger
  • pack up soil oven

Timing:

  • Steve runs to Logan to pick up repaired sonics?. The repairs have been delayed.
  • All drives to/from site (especially TTs) should occur in the morning, when the ground is harder.  Perhaps this means caching stuff on site and removing the caches in the mornings?
  • Steve already there; Clayton arrives 2/23 (last day of ops)
    • strip all towers of instruments, pack in base
      • start with satellites, since Sebastian won't be available Thurs AM 
      • remove heating stuff from CSATs
      • good luck removing soils!
      • figure out how to pack NR01s with ventillation systems
    • provide some assistance to remove PI sensors
      • sort out NCAR vs. UU radiometers/ventillators (relatively easy: CVF3s to UU, CVF4s to us; Bindered sensors to us, rest to UU)
      • return HRXLs to UU – just cut cables?
      • return CS125s (DC is ISS's, I think)
    • return to remove satellite infrastructure, pack in 16' Penske
      • Rohn towers/bases/guys to 16' Penske
      • solar/job box to 26' Penske
      • manfrotto/booms to 26'
      • cables sorted to base
      • DSMs to 16'
  • RSF tech available?; Tony, Chris arrive 3/2ish
    • coil up supersite power cables, pack in Penske for Boulder
    • help remove cc solar panels (hope we can drive in, or rent tracked vehicle from equipment place, or leave in place till later)
    • remove fencing to 16'
    • pull TTs out to BW road
  • someone pulls Ubiquiti from school roof
  • need to pull out everything from DCS by 1 Mar

...

  • 26' Penske
    • solar panels
    • job boxes
    • manfrottos
    • sonic booms
    • NR01 booms
    • create site boxes?
  • base
    • sonics/EC150s (EC100s with EC150)
    • TRH cases
    • QDPs (top shelf)
    • Otts and stands
    • Soils (1 tub)
    • DC power and data cables (sorted)
    • other sensor cables
    • cell modems
    • spare CFACT DSMs
    • NR01s (with ventillation)
    • v2.8 motes
    • cassette brackets
  • Lidar trailer
    • ISS CS125


Site-by-site:



roadcarrypowerjob boxesladdercomments
lcmuddymediumlight AC, some digging and lots of ice/snow16'

straightforward, better in AM

extra clamp on mast

ccsnow crust (use chains?)drive up?solar (10 racks), break ice/snow3no
dcokdrive uplight AC, ice/snow1nostraightforward
sp
maybe muddy
driveabledrive uplight AC, some snow/ice1nostraightforward, better in AM
shpaveddrive uplight AC, snow/ice1nostraightforward
mhicy patches
either LONG or
(use chains), open bike gatedrive uplight AC, snow/ice13'
pcpavedshortishlight AC, some digging, no snow1nostraightforward
up
probably muddy
driveabledrive upsolar (2 racks), no snow1noaccess when frozen
mwokshortlight AC, no snow16'straightforward
prsmuddydrive upheavy AC, transformers, no snow28'a lot of work, plus fence
dcsmuddydrive upheavy AC, transformers, break ice 3 spots28'a lot of work, plus 3xfences

Anything muddy, plan to drive in/out in morning.  Rent a UHV to shuttle in and out of MH and CC?

...