Steve runs to Logan to pick up repaired sonics?. The repairs have been delayed.- All drives to/from site (especially TTs) should occur in the morning, when the ground is harder. Perhaps this means caching stuff on site and removing the caches in the mornings?
- Steve already there; Clayton arrives 2/23 (last day of ops)
- tear down entire site into pickup and Penske; transfer pickup stuff into base
- start with satellites, since Sebastian won't be available Thurs AM
- remove heating stuff from CSATs
- add washers to CSATs?
- good luck removing soils!
- figure out how to pack NR01s with ventillation systems
- provide some assistance to remove PI sensors
- sort out NCAR vs. UU radiometers/ventillators (relatively easy: CVF3s to UU, CVF4s to us; Bindered sensors to us, rest to UU)
- return HRXLs to UU – just cut cables?
- return CS125s (DC is ISS's – E3412)
- packing:
- Rohn towers/bases/guys to 16' Penske
- solar/job box to 26' Penske
- manfrotto/square booms to 26'
- other booms (including all TT) to 16'
- cables sorted to base
- DSMs to 16'
- tear down entire site into pickup and Penske; transfer pickup stuff into base
- Dexter available 3/1ish; Tony, Chris arrive 3/2ish
- move solar panels, job boxes, manfrottos, etc from 16' to 26' Penske
- coil up supersite power cables, pack in 16' Penske for Boulder
- help remove cc solar panels (hope we can drive in, or rent tracked vehicle from equipment place, or leave in place till later), if not already done
- remove fencing to 16'
- pull TTs out to BW road, if not already done
- someone pulls Ubiquiti from school roof
- need to pull out everything from DCS by 1 Mar
...
- Trailer Transit for base to SWEX (Dan did, pickup on 4 Mar afternoon)
- loaded with
- all sensors
- a few CFACT DSMs as spares
- cell modems pulled from CFACT DSMs
- loaded with
- Trailer Transit for TTs back to Boulder (Dan did, 26', pickup on 4 Mar from BestWestern)
- Penske from Boulder to bring SWEX infrastructure (Dan did, pickup 2/28 from Loveland)
- PAM tripods; booms; clamps
- more job boxes/batteries?
- SWEX DSMs
- Penske in Heber to return to Boulder (Dan did, 16', pickup 2/23 from Strawberry). Load infrastructure directly into this.
- power cables/transformers
- Rohn towers
- thermocouple motes
- anything dead (solar panels with bad connectors, etc.) "bad stuff"
- v2.7 stuff, Kipp&Zonens, ventillatorsCVF4s and cables
- bulk of CFACT DSMs
- round booms
Issues:
- Leave ventillation on NR01s, plugs into DSM AUX for power
- Does Bill want wants his CS125 in Boulder or SWEX?to go to SWEX
Organized by location:
- 16' Penske
- Power cables (all), probably need to be removed from field via pickup
- transformers
- TT generators
- Rohn towers (all), base plates, guys/straps
- most CFACT DSMs
- fencing stuff
- thermocouple interfaces
- sonic heater stuff
- CVF4s
- Kipp&Zonens
- used SHT85s
- v2.7 motes
- round TRH booms?
- TT brackets
- bad stuff
- some TRHs
- a DSM
- a mote
- the LC sonic?
...