- About 7am, the ISS1 trailer was dropped off. It is now parked just outside the gate.
- About 10am, the trailer tower was dropped off. I transferred it to the silver truck and took it all the way to its final location in the field, in the correct orientation. In the process, I did manage to get stuck in soft sand, but powered through in 4low. It should be better coming out on the track I'm beginning to establish. I don't have the outrigger feet yet (coming soon), so didn't even try to set them. Cell phone GPS: 38d 02.147'N, 117d 05.407'W. Using a handheld compass, the orientation seemed to be close to 80-12deg declination = 68deg.
- Ran into Town wastewater people unfortunately adding to the pond. Ralph also was the guy who delivered our porta potty, but to the wrong location. He'll move it Monday.
...
- Blaze a track to the tower line for vehicle access
- Finish the last flagging point (just one)
- Drop the chem shelter for the DTS stuff
- Empty out the seacontainer, distributing tower sections/base plates/solar panels to their respective positions
- If time, grab TT feet and set the TT legs
- Sometime, could flag the odd-numbered towers as well (and check the tower line with a measuring tape)