September 28, 2012
Chris and Lisa
All equipment has been removed from the Turbulence Tower. Three sonics, two Licors, five TRHs, barometer, 4-comp, dsm, ALL cables (except eth), batteries, charger.
Things that we kept there were all TRH booms, barometer boom, three sonics booms, CSAT electronic plates (3), 4-comp boom WITH mounting plate and deer stand.
Gear that is in EOL: Five TRHs, two sonic booms, three CSAT electronic plates, 4-comp, barometer, three batteries, power cable and splitters.
Most gear was sent to SCP due to lightening strike on September 27th. At this point I will go through cables and repair as much as I can with what supplies we have in the lab. Most cables need repair.