Today was a little colder than it has been, and started off calm with clear skies with some clouds that moved in by the afternoon.
Nothing exciting happened as far as ISS instrumentation. The profiler remains running well after yesterdays fix. Most of the day I assisted Matt in lowering both towers to replace some of the thermocouples. There is one that I will need to troubleshoot a little more tomorrow as a replacement did not fix the issue.
Todays sounding went fairly well. I did have to reboot the computer as the preparation screen never brought up the ground check countdown and the software seemed stuck at the frequency. This helped and there were no other issues. Also the tether sonde was setup today and I think in the next couple days they plan to have a test flight.