Warm and some clouds. Sebastian came to help and collect the remaining UU equipment.
CC: Used the forklift and lots of muscle to completely teardown this site.
UP: Removed this site. Again, the soil heat flux plate was tilted off horizontal by about 5 deg and sensors in general seemed deeper, likely due to the organic layer (grasses) that makes the surface difficult to define (especially when frozen).
MH: Matt just tugged and both stakes came free. Took less time than it took me to text Chris on another subject!
Organized/packed base and Penskes. Still have a bit to do.
Remaining task: remove stuff (including transformers and job boxes) left at DCS and sort. Then watch the base and maybe TTs go byebye.