This morning Nagios showed that the ISS3 sounding computer was down so we suspected it's the same issues we have had with the UPS. When Lou and I got there the UPS was off so I turned it back on and everything booted up fine. We had stopped at the ACE and grabbed a digital clock to plug into the UPS to see what the time difference is the next time. There had been no indication of a power outage as the other electric clock in the trailer read the correct time.
Next we went to ISS2 since the plots had not updated for the CL51. We went to make sure the files were still saving since Nagios did not indicate any issues with data. Once we verified the files were still saving, I called Isabel to help fix the issue. She found that her work the other day created a bug in the script and she was able to get everything fixed.
I head back to Boulder tomorrow and Isabel safety made it to Santa Barbara to take my spot.