Preparing:

  • inventory: job boxes, manfrottos, otts, shts, ???
  • TT license plates
  • OTTs to base from lidar trailer

Timing:

  • Steve runs to Logan to pick up repaired sonics?. The repairs have been delayed.
  • All drives to/from site (especially TTs) should occur in the morning, when the ground is harder.  Perhaps this means caching stuff on site and removing the caches in the mornings?
  • Steve already there; Clayton arrives 2/23 (last day of ops)
    • strip all towers of instruments, pack in base
      • start with satellites, since Sebastian won't be available Thurs AM 
      • remove heating stuff from CSATs
      • good luck removing soils!
      • figure out how to pack NR01s with ventillation systems
    • provide some assistance to remove PI sensors
      • sort out NCAR vs. UU radiometers/ventillators (relatively easy: CVF3s to UU, CVF4s to us; Bindered sensors to us, rest to UU)
      • return HRXLs to UU – just cut cables?
      • return CS125s (DC is ISS's, I think)
    • return to remove satellite infrastructure, pack in 16' Penske
      • Rohn towers/bases/guys to 16' Penske
      • solar/job box to 26' Penske
      • manfrotto/booms to 26'
      • cables sorted to base
      • DSMs to 16'
  • RSF tech available?; Tony, Chris arrive 3/2ish
    • coil up supersite power cables, pack in Penske for Boulder
    • help remove cc solar panels (hope we can drive in, or rent tracked vehicle from equipment place, or leave in place till later)
    • remove fencing to 16'
    • pull TTs out to BW road
  • someone pulls Ubiquiti from school roof
  • need to pull out everything from DCS by 1 Mar

Need to arrange:

  • Trailer Transit for base to SWEX (Dan did, pickup on 4 Mar afternoon)
    • loaded with
      • all sensors
      • a few CFACT DSMs as spares
      • cell modems pulled from CFACT DSMs
  • Trailer Transit for TTs back to Boulder (Dan did, 26', pickup on 4 Mar from BestWestern)
  • Penske from Boulder to bring SWEX infrastructure (Dan did, pickup 2/28 from Loveland)
    • PAM tripods; booms; clamps
    • more job boxes/batteries?
    • SWEX DSMs
  • Penske in Heber to return to Boulder (Dan did, 16', pickup 2/23 from Strawberry).  Load infrastructure directly into this.
    • power cables/transformers
    • Rohn towers
    • thermocouple motes
    • anything dead (solar panels with bad connectors, etc.)
    • v2.7 stuff, Kipp&Zonens, ventillators
    • bulk of CFACT DSMs

Issues:

  • Leave ventillation on NR01s, plugs into DSM AUX for power
  • Does Bill want his CS125 in Boulder or SWEX?

Organized by location:

  • 16' Penske
    • Power cables (all), probably need to be removed from field via pickup
    • transformers
    • TT generators
    • Rohn towers (all), base plates, guys/straps
    • most CFACT DSMs
    • fencing stuff
    • thermocouple interfaces
    • sonic heater stuff
    • CVF4s
    • Kipp&Zonens
    • used SHT85s
    • v2.7 motes
    • round TRH booms?
  • 26' Penske
    • solar panels
    • job boxes
    • manfrottos
    • sonic booms
    • NR01 booms
  • base
    • sonics/EC150s/EC100s
    • TRH cases
    • QDPs
    • Otts
    • Soils
    • DC power and data cables (sorted)
    • other sensor cables
    • cell modems
    • spare CFACT DSMs
    • NR01s (with ventillation)
    • v2.8 motes
  • Lidar trailer
    • ISS CS125


Site-by-site:



roadcarrypowerjob boxes

lcmuddymediumlight AC, some digging1

ccsnow crust (use chains?)drive up?solar3

dcokdrive uplight AC1

spmaybe muddydrive uplight AC1

shpaveddrive uplight AC1

mhicy patcheseither LONG or drive uplight AC1

pcpavedshortishlight AC, some digging1

upprobably muddydrive upsolar1

mwokshortlight AC1

prsmuddydrive upheavy AC, transformers2

dcsmuddydrive upheavy AC, transformers2

Anything muddy, plan to drive in/out in morning.