CCSM/ESMF Stage-1 Release Schedule

Erik Load: 4.0 actual/ideal
250lpd (new code)
400lpd (outside code)
100lpd (current code)
!!Pre-ESMF Stage

Milestone 3 – Subroutinization / Driver Level (Done! October 3rd)

  • Subroutinize CLM (done)
  • cam3_2_3 Make ICE,OCN into modules – (DONE!) June/29th Erik [,,4kl]
  • cam3_2_15 Institute general high level structure – (DONE!) August/22nd Erik [3.3,1.5w,6kl]
  • cam3_2_17 Resolve non-physics modes in driver / Move restart – (DONE!) August 30th [2, 4d]
  • cam3_2_24 Create initial cut of cam_comp – (DONE!) September 22nd [4.2, 3d, 4kl]
  • cam3_2_24 Cleanup camice – (DONE!) October/3rd Erik [2, 2d]
  • cam3_2_24 Cleanup camocn/somocn – (DONE!) October/3rd Erik [1.5, 2d]
    !!ESMF Stage

    Milestone 4 – All ESMF Components (14 months) (Done Jan)

  • 4.0 (DONE) Put in WRF ESMF time-manager code – (cam3_2_35 created!) Completed Nov 8th [2.5, 2w, 9kl] (Erik)
  • 4.1 (DONE) Erik vacation/sick [4w]
  • 4.2 (DONE) Erik other tasks, SEWG, performance-review [1w]
  • 4.3 (DONE) Output decomposition information to files that Peggy can use – Completed Feb. 15 [1w] (Erik)
  • 4.4 (DONE) Separate coupling layer out for the MCT version – 8 weeks Completed Mar. 16 (cam3_3_1) [8w] (Mariana) (cam3_3_0) [2w Erik time]
  • 4.5 (DONE) Update esmf_wrf_timemgr. Use shr_file_mod for file gets and puts (cam3_3_4) – Completed May 2nd [8,3d,6kl]
  • 4.6 (DONE) CCSM workshop, ESMF workshop [1w]
  • 4.7 (DONE) Create new top level driver. Move to ESMF clocks passed in and driver namelist – Completed: Jul 13th [10,14d,11kl]
  • 4.8 (DONE) Create ESMF branch – Completed: Jul 13th
  • 4.9 Create ESMF driver and coupling code (seq_esmf/ and seq_esmf_drv) – (DONE) (taken: Erik), Completed Jan

    Milestone 5 – Validation (4 months) (Target Date: May 2007)

  • Give Stage-code to ESMF, let them evaluate feedback to us, while testing performed. (DONE)
    https://svn-ccsm-models.cgd.ucar.edu/cam1/branch_tags/esmfStageI02_cam3_3_38
  • Make CAM namelist generation same as cam3_3_38 [currently creates seperate namelist names for dom/som and ice] (taken: Erik)
  • Validation test suite of ESMF for bluesky setup. (DONE) – completed Feb, 8, 2007 (esmfStageI02_cam3_3_38)
  • Stage-I ValidationValidation test suite developed for jaguar and run for bluesky/jaguar. (taken: Samson) (DONE) – complete May, 25, 2007
  • Stage-I Performance Improvement Performance improvements to ESMF Stage-I code. (taken: Samson) (DONE) – complete May, 2007
  • Report to SSC and SEWG about Stage-I.