...
Just to put this in one place: (number of minutes)
- DONE Flip uw.1m sonic (the head to the cassette) (5)
- Upgrade software on snow pillows (20)
- DONE Install CSAT3BH (15)
- Seal all CSAT cassette mounts (120)
- Clean radiometers (2m NR01 and 9m K&Zs) (10)
- Another soil sample (10)
- Install wifi extender, attached to cm dcdc power (and swap in 20W dcdc converter) (15)
- DONE In cb and cl, move the ethernet switch power from bank1 to the dcdc terminal on the power panel (bring extra dcdc converters?) (5)
- Check new pillow prompting code that Gary may install (unknown)
- DONE Read guy tensions (20)
- Remove cassettes from spare CSAT3As, if time allows (15)
...