- reconfigure radiometers into operational mode at dcs and prs. Have new mounting for 0.5m radiometer "paddles".
- move CVF4 Rlws to darkhorse
- move other paddles to 0.5, 7, and 32m (booms for 7 and 32 are on site at each site) – lots of cables to redo. Sebastian will help.
- attach thermocouples and loggers to towers at dcs and prs. Eric said he'd do most of this work.
- raise both TTs
- test heating scripts
Standard operations:
- finish recording serial numbers (a table has been started in this wiki)
- take site photos (maybe Dan has already done?)
- shoot boom angles (compass, then Leica)
- take the first set of gravimetric measurements (though freezing soil probably will have moisture that the EC-5 doesn't see).
Software:
- test heating scripts
- why are there still "Early sample...prior to sorting window" errors using prep? I thought our new timing fixed all this!
- why are there frequent "EMERGENCY|SampleOutput: inet:128.117.43.122:30010: IOException: inet:128.117.43.122:30010: send: Message too long, disconnecting" error messages on the DSM consoles?
- create irga_co2/h2o.dat QC files by height for supersites
- update all csat.dat QC files once boom angles are known.