- Set up Soldier Hollow (SH), running power to from the pumphouse.
- Roughly laid out PRS, while dealing with cows. There seems to be a 1m-diameter crater where the soils once were!
- Rolled out power cable and placed transformer at DCS. Didn't plug in or test yet.
- Decided on a strategy for the radiometer comparison. At DCS, we'll use Sebastian's darkhorse for the Rlw comparison, mounting our CVF4 ventillators on one of his plates. Our darkhorse will be deployed with just our Rsw. When we redeploy to the operational configuration, we'll move our CVF4s to our "schwartzenegger"s on our darkhorse, move his CVF3s to his "paddles", mount the paddles using his booms on the TT and using our old Rohn clamps on a separate 5' Rohn tower, and remove Sebastian's darkhorse. At PRS, we'll do essentially the same, though the CVF3s will be mounted to Sebastian's darkhorse using the same paddles as in the operational array.
- Planned creation of a fence, since we can't do much more installation at either supersite without one while the cows are present.
- Took delivery of 5x UU CS125s. We now have these and the UU HRXLs to modify as an indoor activity during the next bad-weather day.
- Tomorrow I plan to work on the TT upper instrumentation while the fence work is going on.